Network Maintenance
Scheduled Maintenance Report for I.T Communications Limited
Completed
The scheduled maintenance has been completed.
Posted Mar 28, 2018 - 18:49 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 27, 2018 - 20:00 BST
Scheduled
We routinely need to carry out maintenance work on our network. This work is required in order to improve our network infrastructure and ensure continued high levels of resiliency, reliability and scalability.

We will be shutting down all public peering at London Linx 1 and 2 for up to 30 minutes to enable us to increase our bandwidth with London Linx from 2 Gbps to 4 Gbps on 27/03/2018 between 8PM-9PM on 27th March 2018.

Before we shutdown any peers, we will divert the traffic via our IP Transit providers to ensure continued service.

Once the upgrade is completed, we will restore the peering and restore the original routing.
Posted Mar 26, 2018 - 14:10 BST