Network Upgrade Linx London 2
Scheduled Maintenance Report for I.T Communications Limited
Completed
The scheduled maintenance has been completed.
Posted Feb 09, 2021 - 22:00 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 09, 2021 - 20:00 GMT
Update
Sorry, The work will take place on the 9th Feb not the 8th
Posted Feb 08, 2021 - 10:23 GMT
Scheduled
We will be upgrading our connection for London Linx Exchange at Sov House.

The work required will be shifting the Linx's connection from 2 x 1GB Copper Connections to 10Gbps Fibre.

This is the last connectivity connection within our network that is still running legacy copper.

Once this is migrated our core network will be fully on Fibre.

We will shutdown BGP Sessions at 8PM today and wait for traffic to migrate away before doing the required work.
Posted Feb 08, 2021 - 10:21 GMT
This scheduled maintenance affected: Network Infrastructure (London LINX Lon 2).